(Side view from May 2006, before roof was put on.)
February 2007, after roof was put on
2006
2007
God's House International
God's House International
Work done prior to 2006:

Phase 1: Purchased Land (Dec. 2001)
Phase 2: Built fence around property (2002)
Phase 3: Paid Workers to break rocks on land to
initiate building (2002-2003)

Phase 4: Built foundation of building (2001-2003)

2003-2005
- Foundation laid in (March 2003)
- First floor completed
- Cemented 1st floor (the clinic)

2005-2006
- Second floor built
- Plumbing established
- Masonry work started (2005)

Phase 5:

Work done in 2006:
- 3rd floor leveled and covered
- Roof put on
- Masonry work continued

Phase 6:
- Tiled 1st floor
- Plumbing and toilet, windows, electrical work
installed in clinic
Work done in 2007
- Windows and doors put in on 2nd floor
- Masonry work continued